From the first conversation to handover
A villa project goes through eight stages. We go through them together, with the same team, and you always know what comes next and what you receive.
- 01
First conversation and visit
You tell us about the plot, house or penthouse, how you live, your budget and timing. We visit the site and tell you honestly what is possible.
You receiveA written proposal: stages, deliverables and fee.
- 02
Site study and zoning certificate
New builds and extensions onlyWe study the rules that apply to the plot: how much can be built, permitted height, setbacks from neighbours. Then we apply for the zoning certificate for construction, which sets out the approvals, agreements and studies required.
You receiveThe zoning certificate and a clear list of required approvals.
- 03
Concept and 3D
We draw the massing, plans and façades, then the interiors. Every space is rendered photoreal, so decisions are made together on screen, not on site.
You receiveThe architecture and interior concept, 3D renders and material palette.
- 04
Approvals and permit documentation
New builds and extensions onlyWe commission the required studies (topographic survey, geotechnical study), prepare the technical documentation for the building permit and obtain the approvals listed in the zoning certificate. Certified checkers review the design before submission.
You receiveThe complete file, submitted to the competent authority.
- 05
Building permit
New builds and extensions onlyWe follow the file until the permit is issued. Under the new Urbanism Code, the general deadline is up to 30 calendar days from submission of the complete documentation, and on request the permit can be issued in an urgent procedure.
You receiveThe building permit.
- 06
Technical design and detailed interiors
We detail everything that will be built: structure and services with the engineers, bespoke furniture, lighting, finishes. Every piece has a drawing, a material and a quantity.
You receiveTechnical drawings, construction details, material schedules and the budget.
- 07
Construction and site supervision
We coordinate the teams and suppliers, check on site that what is built matches the design, and keep to the schedule. You can choose design supervision only, or full turnkey delivery.
You receiveSite reports and a single point of contact.
- 08
Handover
We install the furniture, tune the lighting, style the rooms and walk through the handover with you. You receive a home ready to live in.
You receiveThe house or penthouse, ready to live in.
For a penthouse or an interior without structural changes, stages 2, 4 and 5 are usually not needed.
What changed with the new Urbanism Code
Law no. 169/2026 (the Code of spatial planning, urbanism and construction) replaced Law no. 50/1991 on building permits.
The general deadline for issuing the building permit is up to 30 calendar days from the complete file. In the urgent procedure, on request, up to 7 working days.
The general validity of the permit for starting works is three years, with extension possible under the law.
Zoning certificates issued before 25 August 2026 remain valid. The exact procedure for files already started is confirmed with the issuing authority.
From 1 November 2028, zoning certificates and building permits in the capital will be issued by Bucharest City Hall (PMB).
The Code introduces a national digital platform for certificates, approvals and permits, becoming mandatory gradually, by August 2031.
Sources:
- Legea nr. 169/2026 – rezumat (storia.ro)
- Wall-Street.ro – termenul de emitere a autorizației
- Economedia – București, emiterea autorizațiilor din 2028
- Forbes România – digitalizarea autorizațiilor
This is general information. For every plot we confirm the applicable rules with the competent authority.
What helps to have at hand
- Title deed and land register extract
- The cadastral or site plan of the plot
- A topographic survey, if one already exists
- An earlier zoning certificate, if you have one
- Your ideas: photos, references, how you live
Frequently asked questions
How long until I get the building permit?
It depends mostly on the approvals listed in the zoning certificate. Once the complete file is submitted, the law sets a deadline of up to 30 calendar days for the permit. We give you a realistic timeline once we see the zoning certificate.
Do I have to handle the approvals myself?
No. We prepare the documents, file the applications and follow every approval. We only need the property documents and your signature where the law requires it.
Can we work on the interiors before the permit?
Yes. The interior concept can run in parallel with the approvals, so when construction starts we already know where the sockets, lighting and bespoke furniture go.
Does a penthouse need every stage?
Usually not. For a penthouse or an interior without structural changes we go straight to concept, 3D, technical design and execution. If the structure or façade changes, we check which permits are needed.