On 25 August 2026 the Code of spatial planning, urbanism and construction, adopted as Law no. 169/2026, came into force. It repealed Law no. 50/1991, which had governed building permits for more than three decades. For anyone building a villa the route still looks familiar, but the changes are worth knowing before you start.
1. Check the plot before anything else
What you can build depends on the zoning rules: the site coverage ratio (POT), the floor area ratio (CUT), the height limit and the setbacks from neighbours and the street. For example, on a 1,000 sqm plot with a maximum coverage of 30%, the footprint generally cannot exceed 300 sqm. If you have not bought the land yet, an information zoning certificate tells you these rules before you sign.
2. The zoning certificate for construction
The new Code distinguishes zoning certificates by purpose: for information, for construction, for demolition and for certain cadastral operations. For a new villa you need the one issued for construction. It is not a permit, but it sets out exactly which approvals, agreements and studies are required. Certificates issued before 25 August 2026 remain valid.
3. Studies, concept and technical documentation
Based on the certificate, the required studies are commissioned, usually a topographic survey and a geotechnical study. In parallel, the architect finalises the concept: massing, plans and façades. With us, this is when the house is rendered in 3D and you can "visit" it before it exists. Then comes the technical documentation for the permit, reviewed by certified design checkers.

4. Approvals: the part that takes longest
The zoning certificate lists the approvals required: utility networks and, where relevant, environment, fire safety or heritage. The new Code allows single-approval committees that bring the authorities together and, in some situations, tacit approval, meaning that no answer within the deadline can count as approval. Note, though, that tacit approval does not apply in every case, and environmental, heritage and safety approvals generally involve separate checks.
5. Filing and the permit
Once the complete file is submitted, the authority has a general deadline of up to 30 calendar days to issue the building permit. At the owner's request, the permit can be issued in an urgent procedure within up to seven working days, although the local authority may do so but is not obliged to. Once issued, the permit is generally valid for three years for starting works, and can be extended under the law.
6. What is different for small houses
The Code introduces a notification procedure for some simpler works, including a single-family house of up to 150 sqm within the built-up area. Instead of a full file, you submit a notification with a simplified technical design, and the response deadline is 15 working days. A luxury villa is usually larger than that, so it follows the full permit procedure.
7. What is coming in Bucharest
From 1 November 2028, all zoning certificates and building permits in the capital will be issued by Bucharest City Hall rather than the sector halls. The Code also creates a national digital platform for certificates, approvals and permits, which will become mandatory gradually, by August 2031.
How long does it really take?
The authorities estimate that, with digitalisation, getting a permit could drop to around 65 days, compared with four to eight months until now. In practice it depends on how many approvals are required and how complete the file is from the start. That is why we begin with the zoning certificate and only then commit to a timeline.
How we help
For the villas we design, we handle the whole route: zoning certificate, studies, approvals, documentation and following the file through to the permit, with the architecture and interiors designed by the same team. The details are on the Architecture & permits page, and every stage is on How we work.
This article is for information only and is not legal advice. For every plot, the applicable rules are confirmed with the competent authority.
Frequently asked questions
Do I need a zoning certificate before buying the plot?
It is not mandatory, but it is very useful. An information zoning certificate shows what can be built on the plot before you buy it.
Is my certificate issued before 25 August 2026 still valid?
Yes. Zoning certificates issued before the new Code came into force remain valid. The exact procedure for files already started is confirmed with the issuing authority.
How long do I have to start building?
The general validity of the permit for starting works is three years, with extension possible under the law.










